Equipment Construction and Start-up Schedule

Schedule begins at time of purchase order and down payment

12 month System construction, installation and startup

Months 8 or 9 2 week supervisory training of owner personnel at manufacturer location

Month 11 4 weeks installation supervision

Month 12 4 weeks start up supervision

 
 