Equipment Construction and Start-up Schedule
Schedule begins at time of purchase order and down payment
12 month
System construction, installation and startup
Months 8 or 9
2 week supervisory training of owner personnel at manufacturer location
Month 11
4 weeks installation supervision
Month 12
4 weeks start up supervision
|